LOW COST CONSTRUCTION

Our Experiences

2.0 Construction with HyperBIM technology and IBS System


Low Cost and Affordable Housing

  • 60 units of Rumah untuk Rakyat Besut, Under the Parliament of Besut, Terengganu

Lekir, Manjung Perak

  • 50 units of My Beautiful New Home Bungalow Houses for B40 under Ministry of Finance in Lekir, Manjung, Perak Darul Ridzuan

Merlimau, Jasin Melaka

  • 50 units of My Beautiful New Home Bungalow Houses for B40 under

Lumut Manjung, Perak

  • Pembangunan Perumahan Perwira Negeri Perak yang Mengandungi 300 unit Rumah Teres Setingkat Di Mukim Lumut Manjung, Perak Darul Ridzuan

Low Cost Houses for B40

50 Units in 100 Days HyperBIM System

by Ascension Technology

Building Information Modelling

HyperBim Low Cost Houses for B40


Progress site work activity:

  1. Concreting work for slab already done casting.
  2. Setting out need to be done on top of the slab before start doing the installation of the formwork.
  3. The installation of the formwork need to referred based on the alignment that have been set up by the license surveyor.
  4. Installation of the formwork started.

Progress site work activity:

  1. Installation of formwork continuously in progress.
  2. BRC installation work started.
  3. Electrical installation work started.

Progress site work activity:

  1. Installation of formwork continuously in progress for exterior and interior of the house.
  2. BRC installation work continuously in progress.
  3. Electrical installation work continuously in progress.

Progress site work activity:

  1. The installation of bracing started once completed install all the formwork.
  2. The installation of the bracing is to ensure that all the formwork are tied strongly before start concreting work.
  3. The method using to fixed the bracing part to the formwork is bolt and nuts method.

Progress site work activity:

  1. Concreting work started.

Progress site work activity:

  1. Formwork dismantle.
  2. Concrete result satisfied.

Progress site work activity:

  1. Roof truss installation work started

Pandangan Hari Ke 75

Eagle Eye View Of Completed Low Cost Houses for B40


HyperBIM

  1. Reduce cost
  2. Deliver on time
  3. Increase productivity
  4. Community participation
  5. New technology (fastbuild + BIM)

Low Cost Housing @ Lekir, Perak Jan 2017 Perak State Gov
Low Cost Housing @ Jasin, Melaka July 2017 Melaka State Gov
PPRT Low Cost Housing @ Kuala Terengganu, Terengganu Nov 2017 Terengganu State Gov
Low Cost Housing @ Kubang Pasu, Kedah Feb 2018 Kedah State Gov
Low Cost Housing @ Marang, Terengganu Feb 2018 Terengganu State Gov